Industrial
|
| Rebar is laid on top of the plywood form and cutout for cement to bond with the 4 ft tall piles. |
|
| The plywood form was held in place with a scaffoldings and aluminum I-beams at the height of the piles. |
|
| Concrete truck, the pump and the suspended slab. |
|
|
| This shows the concrete being placed. |
|
| Level and Height were checked with a laser. |
|
| As the weight of the concrete was added levels were checked all around the suspended slab and adjustments were made. |
|
| Here the cement pump delivers the concrete to the right spot. |
![]() |
| A smooth trowel finish for a good warehouse floor surface finish. |
|
|
| Slab with the forms and scaffoldings removed. |
|
| The Grade was also backfilled. |
|
|
|